Re: Three months until circuits repaired
2 Oct
2001
2 Oct
'01
12:22 a.m.
All, earlier I stated that the West Street C.O. next to the WTC would very likely be gutted, entirely. In a modified approach it now appears that four floors of the building will continue to support limited carrier system and switching operations, while the remainder of the building is done anew. Once done, the four floors that are now still operational will be treated similarly. No time-to- completion date has been given yet. -FAC
How many people still have circuits outside of New York City down? I've heard Worldcom is telling people they won't have everything repaired before December 31. Is this similar for all carriers?
8483
Age (days ago)
8483
Last active (days ago)
0 comments
1 participants
participants (1)
-
Frank Coluccio