On 04/15/2011 09:25 AM, Charles Mills wrote:
I've had it done in places where I work where you'll have 3 rotations working 12 hour shifts.
In a 2 week pay period they get their 80 hours in a blend 36 one week and 44 the next. It gives some nice consecutive days off time which also doubles as a retention tool for some employees. You might have to get creative to have all the days work out but it can be done.
On Fri, Apr 15, 2011 at 9:14 AM, harbor235<harbor235@gmail.com> wrote:
If I were going to provide a 365x24x7 NOC, how many teams of personnel do I need to fully cover operations? I assume minimally you need 3 teams to cover the required 24 hr coverage, but there is off time and schedule rotation?
thoughts, experience?
Mike
I worked once in a production plant. They had 4 crews a,b,c,d and worked 6 days on 2 off. It was rotating shifts. As an example crew A worked 6 days 8-4 was off 2 days then started the next shift on 4-midnight, then midnight to 8. So at any one day 3 of the 4 crews were working and the other crew was off. -- Stephen Clark *NetWolves* Sr. Software Engineer III Phone: 813-579-3200 Fax: 813-882-0209 Email: steve.clark@netwolves.com http://www.netwolves.com