What steps are folks taking to maximize run time of emergency generator equipment and battery in NY facilities currently facing diesel supply issues? Are second halves of redundant systems being temporarily taken off line and non-essential loads being shed in a effort to stretch the time to failure? In a previous life, such precutions were referred to as "rigging for reduced electrical power" and proved quite effective. Thanks, -Dennis