18 Feb
2008
18 Feb
'08
11:30 p.m.
1MW datacenter takes 177millino kwh over its life.
This doesn't seem right 1,000 kw * 24 h * 30 d = 720,000 kw-hrs/mo 177,000,000 / 720,000 = 245 months = 20 years Lot of datacenters last 20 years? Very interesting otherwise, I am very sorry I missed it. I'd love to be part of the next panel. NANOG should focus more on this, as datacenter dynamics (and all the fun stuff to go along with it) is much more of an issue than how to put a 10g wave on dark fiber. alex@nac.net, 1.8 megawatts in 07927, 0.8 megawatts in 07054 (and we painted our roof white, dropped surface temp from 160 to 105 in a 90 sunny day)