Anyone have recommendations (tested/practical is best :-)? First bond the cable shield to earth at the entry point in both buildings. Second use a Tripplite DNET-1 at both buildings. make sure you have a single
On Tuesday 13 September 2005 03:24 pm, R.P. Aditya wrote: point ground terminal that everything it bonded to and then that is grounded. I am in the chicago area, and have towers and locations that have ethernet cables running up to radios. We use this meathod, and don't have problems. Worst we had after last night's T-storm was a site with out power :-) -- Bryan Fields Chief RF Engineer/Partner illiana.net 219-306-1805