On Tue, 22 Oct 1996, Paul Ferguson wrote:
Second, test redundant systems through to resumption of normal operations. In this case, the operators had tested to ensure that the redundant systems would come online in the event of a failure of the primary system. They had not tested to see what would happen when the primary system was restored to normal operation.
Who would have even thought about it? I confess that I would not have.
William Hugh Murray, New Canaan, Connecticut
Greetings, As a rule we exercise our generator under load every Thursday at 1000hrs. I would like to do this monthly but, the automatic exercise mechanism cannot deal with 30 day intervals. In addition, once every 6 months, we simulate a power outage by switching off and on the main breaker at the service entrance durig a traffic lull period. Cheers Patrick J. Chicas Email: pjc@unix.off-road.com URL: http://www.Off-Road.com -------------------------------- The Off-Road Center of The 'Net!