On Wed, 2024-12-18 at 16:27 -0500, Sean Donelan wrote:
Utility hired subcontractors don't show up on time when a builder has the utility trenches open, or they show up months/years afterwards. Damage things digging up utility right-of-ways, that the developer has to repair.
A friend was involved in a development project in a regional town. They specified conduits everywhere. When the network people showed up at some random later date, they mostly just had to pull stuff through existing conduits. Not sure of the details beyond that, but he reckoned it cost a lot less that doing it all later.
Cable 134.4 million households (82%) DSL 7 million households (4%) Fiber 74.9 million households(46%) Fixed wireless 77.3 million households (47%) Satellite 162.8 million households (99%)
What are the percentages? Regards, K. -- ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Karl Auer (kauer@biplane.com.au, he/him) http://www.biplane.com.au/kauer