14 Apr
2005
14 Apr
'05
9:07 p.m.
On Thu, 14 Apr 2005, Randy Bush wrote:
you'll never get better redundancy than having more than one carrier.
very often, they buy segments from eachother, run in the same trench, change the dlr six months later, ... trust and test just as you would a single carrier. trust 0 test 100.
when this has been critical i've insisted on seeing duct maps to ensure they really are different. but as you say even that doesnt prevent a change of path in the future i guess it helps us to know a bit more than the average circuit buyer tho too.. Steve